Suzhou Electric Appliance Research Institute
期刊號(hào): CN32-1800/TM| ISSN1007-3175

Article retrieval

文章檢索

首頁 >> 文章檢索 >> 往年索引

智能變電站220 kV線路保護(hù)檢修安全措施方案研究

來源:電工電氣發(fā)布時(shí)間:2018-10-16 14:16 瀏覽次數(shù):612
智能變電站220 kV線路保護(hù)檢修安全措施方案研究
 
李敏
(國網(wǎng)江蘇省電力有限公司檢修分公司,江蘇 常州 213000)
 
    摘 要:智能變電站在二次回路上的高度網(wǎng)絡(luò)化,使得二次回路物理結(jié)構(gòu)模糊,給檢修安全措施實(shí)施帶來不便。分析了智能站二次設(shè)備新功能特征和安全措施,以220 kV線路間隔為例,討論了線路間隔常規(guī)校驗(yàn)和缺陷處理中涉及到的二次安全措施的實(shí)施。為確保二次虛回路的安全隔離,智能變電站安全措施的實(shí)施至少采取雙重安全措施。在不破壞網(wǎng)路結(jié)構(gòu)即不插拔光纖的情況下,安全措施的實(shí)施原則主要按照投入檢修壓板、退出出口軟壓板、退出接收軟壓板來實(shí)施隔離,設(shè)置安全防線。
    關(guān)鍵詞:智能變電站;二次回路;安全措施;檢修機(jī)制
    中圖分類號(hào):TM63;TM755     文獻(xiàn)標(biāo)識(shí)碼:A     文章編號(hào):1007-3175(2018)10-0039-04
 
Safety Measure Schematic Study on 220 kV Line Protection Overhaul in Intelligent Substation
 
LI Min
(State Grid Jiangsu Electric Power Co., Ltd, Maintenance Company, Changzhou 213000, China)
 
    Abstract: The highly networking of secondary circuit in intelligent substation makes the physical structure of secondary circuit fuzzy, which causes inconvenience for overhauling safety precautions implementation. This paper analyzed the new function characteristics and safety precautions and took the 220 kV line interval for example to discuss the line interval convention verification and the secondary safety precautions implementation involved in the defects treatment. To guarantee the safety isolation of secondary virtual circuit, at least double safety precautions were adopted for the implementation of intelligent substation safety precautions. Under the conditions of non-destroying the network structure, non-insert-pullout optical fiber, the implementing principle of safety precautions mainly followed inputting overhaul pressing plate, quitting exit soft pressing plate, quitting accepting pressing plate to implement isolation and to set the safety defense line.
    Key words: intelligent substation; secondary circuit; safety precaution; overhauling mechanism
 
參考文獻(xiàn)
[1] 徐曉春,湯同峰,趙雨田,都晨. 智能變電站二次設(shè)備檢修安措規(guī)則數(shù)據(jù)庫設(shè)計(jì)與實(shí)現(xiàn)[J]. 電力系統(tǒng)保護(hù)與控制,2017,45(2):111-116.
[2] 馬義,張鈺金,錢苗旺,胡志勇. 智能變電站與傳統(tǒng)變電站若干關(guān)鍵技術(shù)比較[J]. 江蘇電機(jī)工程,2016,35(6):77-78.
[3] 彭少博,鄭永康,周波,李小鵬.220 kV智能變電站檢修二次安措研究[J]. 電力系統(tǒng)保護(hù)與控制,2014,42(23):143-148.