特高壓工程絕緣油交接試驗(yàn)問題分析

來源:電工電氣發(fā)布時(shí)間:2020-06-18 13:18 瀏覽次數(shù):959
特高壓工程絕緣油交接試驗(yàn)問題分析
 
董然,馬衛(wèi)華,劉振,王艷,劉波
(國(guó)家電網(wǎng)有限公司交流建設(shè)分公司,北京 100032)
 
    摘 要:根據(jù)現(xiàn)行的絕緣油試驗(yàn)相關(guān)標(biāo)準(zhǔn)及施工驗(yàn)收規(guī)范,結(jié)合以往特高壓工程建設(shè)經(jīng)驗(yàn)及試驗(yàn)單位調(diào)研意見,對(duì)特高壓工程絕緣油試驗(yàn)項(xiàng)目?jī)?nèi)容及劃分、試驗(yàn)標(biāo)準(zhǔn)、試驗(yàn)費(fèi)用等進(jìn)行了梳理分析,并給出了預(yù)算定額及技術(shù)規(guī)程修訂完善的意見與建議。以期減少在特高壓工程建設(shè)管理過程中交接試驗(yàn)環(huán)節(jié)的專業(yè)協(xié)調(diào)工作,為后續(xù)特高壓工程絕緣油交接試驗(yàn)工作規(guī)范開展與費(fèi)用計(jì)列提供合理依據(jù)。
   關(guān)鍵詞:特高壓工程;絕緣油;交接試驗(yàn)
   中圖分類號(hào):TM855     文獻(xiàn)標(biāo)識(shí)碼:A     文章編號(hào):1007-3175(2020)06-0062-03
 
Analysis on Problems of Insulation Oil Commission Test in UHV Project
 
DONG Ran, MA Wei-hua, LIU Zhen, WANG Yan, LIU Bo
(State Grid AC Engineering Construction Company, Beijing 100032, China)
 
    Abstract: According to the current insulating oil test related standards and construction acceptance specifications, and combined with previous UHV project construction and the survey advises of relevant units, The content and division, test standards, test costs, etc. of insulating oil test items for UHV project were combed and analyzed, and suggestions and suggestions for budget quota and technical regulations revision were given. In order to reduce the professional coordination of the commission test in the UHV project construction management process, and provide a reasonable basis for the follow-up UHV project insulation oil commission test work specification and cost calculation.
    Key words: UHV project; insulating oil; commission test
 
參考文獻(xiàn)
[1] 中國(guó)電力企業(yè)聯(lián)合會(huì).1 000 kV系統(tǒng)電氣裝置安裝工程電氣設(shè)備交接試驗(yàn)標(biāo)準(zhǔn):GB/T 50832—2013[S]. 北京:中國(guó)計(jì)劃出版社,2013:37-39.
[2] 全國(guó)石油產(chǎn)品和潤(rùn)滑劑標(biāo)準(zhǔn)化技術(shù)委員會(huì)石油燃料和潤(rùn)滑劑分技術(shù)委員會(huì). 電工流體 變壓器和開關(guān)用的未使用過的礦物絕緣油:GB 2536—2011[S]. 北京:中國(guó)標(biāo)準(zhǔn)出版社,2011:8-12.
[3] 中國(guó)電力企業(yè)聯(lián)合會(huì). 電氣裝置安裝工程 電氣設(shè)備交接試驗(yàn)標(biāo)準(zhǔn):GB 50150—2016[S]. 北京:中國(guó)計(jì)劃出版社,2016:58-60.
[4] 國(guó)家能源局. 電力建設(shè)工程預(yù)算定額 第五冊(cè) 調(diào)試工程[M]. 北京:中國(guó)電力出版社,2013.